To approve the updated scope and budget of the project, proceed with construction contract and relevant delegations to officers.
I. That a revised capital budget of £31,137,252, as shown in the financial viability assessment at Exempt Annexe 1, be agreed to deliver a new-build Cranleigh Leisure Centre;
II. That the leisure centre is built to Passivhaus certification standards;
III. That authority be delegated to the Joint Director for Place, in consultation with the relevant portfolio holder, to submit a planning application in respect of the proposed new build;
IV. That authority be delegated to the Joint Director for Transformation and Governance, in consultation with the relevant portfolio holder, to conduct the procurement of a contractor for the build and all related professional services, including, but not limited to, the Employers Agent and Design team;
V. That authority be delegated to the Joint Executive Head of Legal and Democratic Services to complete and execute all necessary contractual documents.
Report author: Kelvin Mills
Publication date: 04/10/2023
Date of decision: 03/10/2023
Decided at meeting: 03/10/2023 - Executive
Effective from: 12/10/2023