Decision Maker: Executive
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
It is recommended that the Executive approve the discretionary projects and their proposed funding for the 2021-22 Capital Programme as listed in Annexe 1.
RESOLVED that
1. The Asset Management Plan (AMP) produced by the Engineers for pavilions across the Borough and the RAG rating to prioritise works that are now critical be noted
2. The value of up to £76,080* be approved from the 2021-22 capital budget
[*full amount subject to clarification of approved works with Bourne Community Group].
Reason: For urgent maintenance works required to Waverley pavilions to take place now that a strategic AMP has been produced.
[Services Overview and Scrutiny]
Report author: Kelvin Mills
Publication date: 19/01/2022
Date of decision: 18/01/2022
Decided at meeting: 18/01/2022 - Executive
Effective from: 27/01/2022
Accompanying Documents: