Decision details

Weydown Road Development Project

Decision Maker: Executive

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To receive recommendations.

Decision:

The Executive RESOLVED to approve:

 

       I.          A Supplementary Budget of £223,298 for the purposes of progressing Weydown Road Community Hub Option B to submission of planning application (RIBA stage 3) and associated site surveys.

     II.          Progression of the Weydown Road Community Hub project to submission of a Planning Application.

   III.          Delegated authority to the Strategic Director - Place to submit the required planning applications for this project on behalf of the Council.

  IV.          Delegated authority to the Strategic Director - Place in consultation with the Strategic Director, Legal & Democratic Services to implement the procurement strategy, and award the consultancy services contracts.

    V.          Delegated authority to the Strategic Director - Place in consultation with Strategic Director, Legal & Democratic Servicesand Portfolio Holder for Finance and Assets to approve and implement a procurement strategy for the construction contracts associated with this project.

 

Report author: Debbie Smith

Publication date: 10/04/2024

Date of decision: 09/04/2024

Decided at meeting: 09/04/2024 - Executive

Effective from: 18/04/2024