Cranleigh Leisure Centre New Build

Decision Maker: Executive

Decision status: Recommmend Forward to Council

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To approve the updated scope and budget of the project, proceed with construction contract and relevant delegations to officers.

Decision:

       I.          That a revised capital budget of £31,137,252, as shown in the financial viability assessment at Exempt Annexe 1, be agreed to deliver a new-build Cranleigh Leisure Centre;

 

     II.          That the leisure centre is built to Passivhaus certification standards;

 

   III.          That authority be delegated to the Joint Director for Place, in consultation with the relevant portfolio holder, to submit a planning application in respect of the proposed new build;

 

  IV.          That authority be delegated to the Joint Director for Transformation and Governance, in consultation with the relevant portfolio holder, to conduct the procurement of a contractor for the build and all related professional services, including, but not limited to, the Employers Agent and Design team;

 

     V.          That authority be delegated to the Joint Executive Head of Legal and Democratic Services to complete and execute all necessary contractual documents.

 

Report author: Kelvin Mills

Publication date: 04/10/2023

Date of decision: 03/10/2023

Decided at meeting: 03/10/2023 - Executive

Effective from: 12/10/2023